Newsletter: Motor control center building complete at Grace Way Well project site
Published on May 27, 2026
The motor control center building has been completed at the Grace Way Well site, paving the way for allowing crews to start planning for electrical connections. That process involves trenching on the site as well as part of the road.
Once completed, the Grace Way Well will draw water from the Butano and Lompico aquifers, becoming the District’s sixth active well. Capital Improvement Projects like this are essential for maintaining a reliable water supply for local residents and businesses.
Learn more in the May newsletter.